During the dry dock phase of the RCOH, George Washington underwent significant upgrades and extensive repair work both inside and outside the ship. In addition to defueling and refueling its power plant, Newport News shipbuilders have re-preserved approximately 600 tanks and replaced thousands of valves, pumps, and piping components. On the outside, they performed major structural updates to the island, mast and antenna tower; upgraded all aircraft launch and recovery equipment; painted the ship’s hull, including sea chests and freeboard; updated the propeller shafts, and installed refurbished propellers.
During the next phase of the complex engineering and construction project, shipbuilders will finish up the overhaul and installation of the ship’s major components and test its electronics, combat and propulsion systems before the carrier is redelivered to the Navy. This period also will be dedicated to improving the ship’s living areas, including crew living spaces, galleys, and mess decks.
“Taking the ship successfully out of the dry dock and over to our waterside pier marks a significant moment in the ship's history and in our RCOH period,” said Capt. Kenneth A. Strong, the ship’s commanding officer. “With the ship back in the water, we can turn our attention to our next major milestones and finishing our maintenance period to return this vital national asset back to the fleet.”
USS George Washington arrived at Newport News in August 2017 and is the sixth Nimitz-class aircraft to undergo its RCOH—the mid-life refueling overhaul and maintenance availability that produces a recapitalized carrier capable of supporting current and future warfare doctrine. Once George Washington’s RCOH is complete, the carrier will be equipped to operate in the U.S. Navy fleet for the second half of her 50-year expected service life.