© Chris Goddard | Shutterstock
The Tata Steel plant at Port Talbot, South Wales.

Case Study: Heavy Duty Removals

Aug. 8, 2018
Sulzer moves and refurbishes a 180-ton welder for Tata Steel.

The steel industry requires robust and reliable equipment to maintain productivity, but this ruggedness has to be balanced with a need to integrate new technologies to maintain overall operational efficiency. The sheer scale of plant items such as welders, for example, presents a number of challenges to modernization; hence the need for experienced engineers and designers, such as those at Sulzer, to achieve a seamless update and integration project.

The high cost of new equipment means that relocating and refurbishment of an existing plant can offer a more cost-effective way of maintaining productivity and reliability. The key to completing such a project lies in the expertise and experience of the engineers who are responsible for relocating, redesigning, and reassembling the equipment.

The Avonmouth Service Center has built up an excellent working relationship with a number of customers in the steel, marine, mining, and water industries and has a reputation for completing large mechanical and electrical repairs within tight deadlines. One such example recently completed for Tata Steel required a flash butt welder that was originally located in Port Talbot, to be dismantled, refurbished, relocated, and commissioned on a pickling line in the Llanwern Works.

The flash butt welder weighs more than 180 tons and is positioned at the start of the pickling line and is used to join two rolls of steel together before continuing along the pickling line. Put simply, the machine cuts the tail end of the outgoing coil and the head end of the incoming coil simultaneously ensuring the edges of both coils are parallel to each other before a current is passed between the join, welding both coils together. This process requires precise control and positioning to ensure a high-quality weld for the continuous line process.

The initial part of the project was to dismantle the welder into modules to allow it to be transported by road to Sulzer's Avonmouth Service Center where it was fully dismantled and inspected to perform a complete appraisal. The findings and recommendations were then communicated to allow the customer to decide on the viability of the refurbishment project.

One major design change was to the machine handling and control systems which had to be reconfigured due to the steel strip flow being in the opposite direction in Llanwern. A completely new electrical wiring system and software were installed along with all new hydraulic and pneumatic piping. In addition, new hydraulic valve stands with upgraded hydraulic pumps were also incorporated into the refurbished machine.

While this work was being completed in Avonmouth, in Llanwern the existing machine had to be removed to install new foundations in preparation for the arrival of the refurbished welder. Careful coordination between Sulzer and Tata Steel ensured that the site would be ready and the project timetable would be maintained.

With the upgrades complete the entire welder was reassembled at Sulzer Avonmouth to ensure that all the modifications had been successful and that the operation of the machine met the required Operational Engineering Standard. The ability to complete in-house testing of equipment such as this is an important asset that ensures the Sulzer service center delivers the refurbished equipment without the need to spend precious time resolving glitches.

The fully functioning welder was then dismantled into modules for the final time for the short journey across the Severn Estuary before being reassembled in the Llanwern Works. The Sulzer engineers completed the assembly and the connections with the rest of the production line before functional testing and initial welds were completed. Full production was possible in less than two weeks following delivery to the site; a testament to the planning and the functional testing carried out in Avonmouth.